TRAFFIC ALERT: Upcoming work as part of RapidRide H Line preparations

(Metro photo, 15th/Roxbury)

From Metro, some specifics about upcoming work as part of the RapidRide H Line preparations:

One-block closure: Starting as soon as Aug. 23, work crews will close 15th Avenue SW between 106th and 107th streets to all general traffic. Access to businesses along this corridor will be maintained. The closure is expected to last until October 2021. During the closure, crews will construct:
-infrastructure for the future RapidRide H Line stations.
-new sidewalks, curbs, and ADA compliant ramps
-a new pedestrian signal crossing at SW 107th Street.

The southbound bus stop at 15th and 106th Street and northbound stop at 15th and 107th Street will be closed during construction. Please use stops north of 106th or south of 107th streets

Nighttime utility installations: Starting as soon as Aug. 23, crews will be working at night to install new underground utilities across the width of 15th Avenue SW from the southeast to southwest corners of the 15th Avenue SW and SW Roxbury Street intersection. Nighttime work in this location is expected to be ongoing through the end of August. During this work:
-The sidewalk and both lanes of traffic on 15th Avenue SW will be closed from the intersection south to mid-block between SW Roxbury Street and SW 98th Street
-Crews will be working weekday nights between 9 p.m. and 5 a.m.
-Detours will be in place for people driving, walking, and rolling
-Access to driveways and businesses will be maintained.

Daytime sidewalk and curb construction: Crews will be installing new sidewalks and curbs along 15th Avenue SW near the SW Roxbury Street intersection starting as soon as Aug. 23. This work is expected to be ongoing through early September. During this work:
-Crews will be working weekdays between 7 a.m. and 3:30 p.m.
-Sidewalk and traffic lane closures will be in place
-Detours will be in place for people driving, walking, and rolling
-Access to driveways and businesses will be maintained.

Nighttime drainage work: On Aug. 25 and 26, work crews will perform nighttime drainage work at SW 102nd Street between 15th Avenue SW and 16th Avenue SW. During this work:
-Crews will be working between 9 p.m. and 5 a.m.
-Traffic will be reduced to one lane and be guided by flaggers.

Metro Route 120 is scheduled to convert to the H Line in fall 2022.


You can follow any responses to this entry through the RSS 2.0 feed. Both comments and pings are currently closed.

AddThis Social Bookmark Button

2 Responses to “TRAFFIC ALERT: Upcoming work as part of RapidRide H Line preparations”

  1. Wow! Thanks for the info!

  2. Karen Therese Says:

    It’s Infrastructure month in Rat City!