ROAD-WORK ALERT: SW 104th work starts today – first phase of big 16th SW project
The big 16th SW project is about to start. First, work starts today on pipelines under part of 104th. Here’s the phasing as detailed by King County Roads:
Construction will last about six weeks in three phases. Expect detours, temporary road closures, and no-parking zones at different times. Businesses will remain open! The anticipated construction dates below are subject to change due to crew or material availability.
Phase 1: March 3 – April 18
Where: SW 104th Street Between 15th Avenue SW & 16th Avenue SW
What’s happening: Replacing drainage pipes under the north side of the road
Impact: Limited parking for duration of the project, lane restrictions
Access: Local access will be open, and businesses will remain openPhase 2: March 11 – April 1 – Intersection Closure at 16th Avenue SW & SW 104th Street
Where: The north half of the intersection where 16th Avenue SW meets SW 104th Street will be closed to all through traffic, including pedestrians and bikes.
What’s happening: Pipe replacement under the intersection
Impact: The intersection will be fully closed for two weeks. More time may be needed, depending on weather and equipment availability.
Access: Local access will be maintained on 16th Avenue SW on both sides of the road closure, and businesses will remain openDetour route:
Northbound (toward SW Roxbury St.): SW 102nd St → 15th Ave SW → 16th Ave SW
Southbound: (toward SW 107th St.) SW 106th St → 15th Ave SW → 16th Ave SWPhase 3: April 2 – April 18 – Limited Parking on SW 104th Street
Where: SW 104th Street between 16th Avenue SW & 17th Avenue SW
What’s happening: Final pipe replacement under the road
Impact: Limited parking for 1-2 weeks
Access: Local access will be maintained, and businesses will remain open